| Cost Item | Quantity | Cost/Item | Total $ | | Land Purchase | | | |
| Land Purchase | 1.00 Each | 2,000,000.00 | 2,000,000.00 |
| Total Land Purchase | | | $2,000,000.00 |
| | | |
| Construction | | | |
| Construction Spending | 20,000.00 Each | 60.00 | 1,200,000.00 |
| Total Construction | | | $1,200,000.00 |
| | | |
| Contigency | | | |
| Hard Cost Contigency | 1.00 Each | 35,000.00 | 35,000.00 |
| Total Contigency | | | $35,000.00 |
| | | |
| Site Work | | | |
| General Conditions | 1.00 Each | 40,000.00 | 40,000.00 |
| Trash Enclosures | 1.00 Each | 9,500.00 | 9,500.00 |
| Clearing & Grading | 1.00 Each | 23,000.00 | 23,000.00 |
| Storm Drainage | 1.00 Each | 35,000.00 | 35,000.00 |
| Site Concrete | 1.00 Each | 23,000.00 | 23,000.00 |
| Sub Base paving | 1.00 Each | 30,000.00 | 30,000.00 |
| Building Pad stabalization | 1.00 Each | 10,000.00 | 10,000.00 |
| Site Utilities | 1.00 Each | 25,000.00 | 25,000.00 |
| Site Electric-Lighting | 1.00 Each | 40,000.00 | 40,000.00 |
| Signage | 1.00 Each | 25,000.00 | 25,000.00 |
| Landscape & Irrigation | 1.00 Each | 20,000.00 | 20,000.00 |
| Contg. | 1.00 Each | 30,000.00 | 30,000.00 |
| Total Site Work | | | $310,500.00 |
| | | |
| Building Other | | | |
| Sewer Capacity | 1.00 Each | 5,000.00 | 5,000.00 |
| Water Fee's | 1.00 Each | 2,000.00 | 2,000.00 |
| Electricial Fee's | 1.00 Each | 5,000.00 | 5,000.00 |
| Permits-Zoning-Review Fee's | 1.00 Each | 3,000.00 | 3,000.00 |
| Plan Copies | 1.00 Each | 500.00 | 500.00 |
| Developers Liability Insurance | 1.00 Each | 12,000.00 | 12,000.00 |
| Total Building Other | | | $27,500.00 |
| | | |
| Architectual & Engineering | | | |
| Architects | 20,000.00 SqFt | 3.25 | 65,000.00 |
| Civil Engineering | 1.00 Each | 22,000.00 | 22,000.00 |
| Landscape Design | 1.00 Each | 2,500.00 | 2,500.00 |
| Reimbursable Architects | 1.00 Each | 4,500.00 | 4,500.00 |
| Total Architectual & Engineering | | | $94,000.00 |
| | | |
| Soft Costs | | | |
| Legal | 1.00 Each | 45,000.00 | 45,000.00 |
| Travel to site | 1.00 Each | 800.00 | 800.00 |
| Construction Management Fee | 1.00 Each | 7,500.00 | 7,500.00 |
| Appraisal | 1.00 Each | 4,500.00 | 4,500.00 |
| Survey | 1.00 Each | 3,500.00 | 3,500.00 |
| Title Insurance | 1.00 Each | 3,500.00 | 3,500.00 |
| Total Soft Costs | | | $64,800.00 |
| | | |
| Contigency | | | |
| General Contigency | 1.00 Each | 30,000.00 | 30,000.00 |
| Total Contigency | | | $30,000.00 |
| | | |
| Tenant & Leasing Costs | | | |
| TI for First Floor | 20,000.00 SqFt | 25.00 | 500,000.00 |
| Commisions for First Floor | 20,000.00 Each | 6.00 | 120,000.00 |
| Total Tenant & Leasing Costs | | | $620,000.00 |
| | | |
| Total Project Cost | | | $4,381,800.00 |
|